VNI West will use 500 kV towers, approximately 60–80 metres high, similar to those seen when driving into Melbourne. Towers will have bases of 15–20 m² and be spaced roughly 400 metres apart, depending on terrain.

TCV aims to maximise setbacks from residences and sensitive areas. A typical design guideline is 300 metres between the transmission line and a residence.

Towers will be 60–80 metres high, with the lowest sag point about 15 metres above ground.

The width of the tower arms are expected to range from 25 to 28 metres wide.

The base will cover an area of approximately 15 × 15 metres to 25 × 25 metres, depending on tower type and design.

The easement will be 70–120 metres wide to allow safe operations and maintenance. It will not be fenced, and many farming activities can continue under the lines if safety requirements are met. See the Farming with Transmission Fact Sheet for more information: https://www.transmissionvictoria.com.au/download_f...

Towers are designed for a minimum service life of 70 years. Decommissioning occurs when a line is de-energised and typically involves removal. Costs and remediation are the responsibility of the Transmission Network Service Provider (TNSP).

Approximately 400 metres, varying with terrain.

Some properties may require new access tracks. Details will be agreed in a Property Management Plan (PMP) attached to the easement agreement. The PMP will outline temporary fencing, access crossings, and mitigation measures. Any productivity or access loss will be factored into compensation

No. Double-circuit 500 kV lattice towers at 90° angles are not feasible due to design complexity, increased loading, and larger footings required.